Hi,
Is it possible to assign separate EV calculation method to different activities.
For eg:
Act1: Activity percent complete
Act2: 0/100 method
Act3: 50/50 method etc..
or only one method for the whole project?
Hi,
Is it possible to assign separate EV calculation method to different activities.
For eg:
Act1: Activity percent complete
Act2: 0/100 method
Act3: 50/50 method etc..
or only one method for the whole project?
Welecom
Thanks Thaer...
Hi
it is possible to assign spearate EV Calaculation method to differnet WBS -Level .
Open WBS-Window (Earned Value Tab from WBS Details)
Hi
it is possible to assign spearate EV Calaculation method to differnet WBS -Level .
Open WBS-Window (Earned Value Tab from WBS Details)