Generate Resource loading report in P6

S
Sinan Fahmi 👤 Member for 19 years 5 months

Dear Planners,

  is it possible to generate Resource loading report in P6 as we did previously in P3 and transfer it excel?

Regards,

H
Hannes de Bruyne 👤 Member for 20 years 10 months

 yes - use report wizzard.

 

Subject Area „Activity Resource and Role Assignments“ select „Time Distributed Data"  select columns, fields etc. Finaly output in ASCII File delimited as in EXCEL

  • Regards