I'm comparing this months progress and last months progress. I used last month's programme as a baseline for this month's programme and reflect it in the Gantt Chart. So since I'm using last month's programme as a baseline (just for comparison) there are actual dates for tasks and milestones. No problem with task dependent activities, the problem is with the milestones with actual dates. Instead of showing it behind the data date line, it was shown ahead of the data date line just like a planned date. Anyone knows how to solve this. Thanks.
Milestones with actual dates for baseline
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Gary,
That was very helpful. Thak you very much.
If you don't have the right settings chosen, Primavera will display planned dates instead of actual for baseline projects.
Check the link below for Paul Harris' excellent explanation of this issue
http://www.eh.com.au/Technical%20Papers/110616_P6_V7_What_Baseline_Bars_am_I_Displaying.pdf
Cheers,
G
Hi Ron
If a milestone has been reached and achieved you need to set completion at 100%.
Best regards
Mike Testro