If I have several activities with the same start and finish date, and I am sorting by Start Date, how does P6 determine the order of the activities? It doesn't seem to be alphabetical after start date, is there any way I can change the order of activities which have the same start dates?
Order of activities within WBS
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
If start date are the same, P6 will by default order by activity id.
to change this go to view > group & sort > sort
Use 'add' to include a second sort rule to be applied when start dates are equal