Oh Hi I hope you are doing good
Can you please help me modelling Resource hour in my schedule who works alternate months
So lets assume
if Resource X is working on Package A and he works 2 days in Jan March May July Sept Nov
How do i model this in primavera so it reflect in my activity usage spread sheet like this
Jan Feb Mar Apr May Jun July Aug Sep Oct Nov
2 2 2 2 2 2
Thanks in Advance