Oh HI Guys
I hope you are doing well.
One my resource is working alternatively on my project how do i model this resource hours on my plan
Package A
Resource X
working 2 days Jan , Mar , May, July , Sept , Nov.
I have used suspend activitu but it does not work
Any other suggestions will be appreciated
Dear,
I think the easiest way is to create a calendar based on your working criteria that is alternate months and 2 days working.