Dear,
I am using resources curves in P6, the issue is that after several months I changed one resource curve and the following message pop up in the screen "the new curve definition will not recalculate actual units & costs until the resource assigment is updated". After this message I have tried several thing to solve this problem but the curve does not work, it means that the budget quantities are not distributed along the time. Anybody knows what should I do "update the resource assigment"?.
Thanks in advance
Natalia Barroso. PMP