Resources Curves

Dear,

 

I am using resources curves in P6, the issue is that after several months I changed one resource curve and the following message pop up in the screen "the new curve definition will not recalculate actual units & costs until the resource assigment is updated". After this message I have tried several thing to solve this problem but the curve does not work, it means that the budget quantities are not distributed along the time. Anybody knows what should I do "update the resource assigment"?.

 

Thanks in advance

 

Natalia Barroso. PMP

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts