Hi everyone
I'm hoping the vast well of knowledge out there can help me out of a pickle with a new PM.
Basically, I need to assign a % Weighting to various activities that I can manually enter (not generated by the software) as this figure will be assigned by the workstream owner. I need this figure to roll-up and be shown in summary WBS bars. For example:
WBS = Passenger Services
Activity 1 - % Weighting = 25% - OD = 15d
Activity 2 - % Weighting = 50% - OD = 5d
Activity 3 - % Weighting = 25% - OD = 10d
If Actvity 1 has finished ie RD = 0 and Duration % Comp = 100%, this activity needs to contribute only 25% to the total Weighted % Comp shown under the Passenger Services WBS summary.
I don't mind if I have to update the Weighted % Complete manually, so long as I can show the combined weighted % figure in the WBS Summary bar as I need to produce a Level 2 Summary that shows this data for reporting.
I can't use activity steps to achieve this because the % will become 100% when all steps are achieved, when actually the activitiy in it's entirety is only equal to, say, 60% (weighting as assigned by the owner).
I've also been asked to assign a curve per department/owner, so perhaps a dud resource is of use to - suggestions please?
This is not the way I would normally operate, but it's what the client wants.
I hope this all makes sense, and I'll be really grateful for any help/advice.
Andy
- Log in or register to post comments