Hi Everyone
When I import a XER file sent to me and open it up, the budgeted quantities in the resources has changed – after some investigation I realised each time I import it is dividing the budgeted quantities by 8 – I presume this is because there are 8 hours in the day in the calendar.
Can anyone please advise how this can be avoided?
Thanks
Hi David
P6 is a pig to operate - it may be that you are set to hours and not days or something like that.
In ASTA you can just copy / paste directly from excell.
Why not multply by 8 before importing.
Best regards
Mike Testro