Under Admin Preferences, in addition to entering Hours/Day, is entering the Hours/Week, or Hours/Month and,or Hours/Year necessary ?
As a test case, I entered 8 Hours/Day and 1 Hour/Week and the schedule still seemed fine.
Thanks,
Kashyap Mothali
Under Admin Preferences, in addition to entering Hours/Day, is entering the Hours/Week, or Hours/Month and,or Hours/Year necessary ?
As a test case, I entered 8 Hours/Day and 1 Hour/Week and the schedule still seemed fine.
Thanks,
Kashyap Mothali
This is used for the EPS calculations. Just ignore it and make sure that "Use assigned calendar to specify the number fo work hours for each time period" is checked.
You can find that option in Admin Preferences---->Time Periods----->under Hours per Time Period
it only means consistency, if it isn't, then expect otherwise
The question is where are the Week, Months or Year data used? If you say 8 hrs/day and yet, set Hours/Week, Month or Year as 1, the schedule is still fine.
Is it when the schedule is calculated in month, that hours/month come into play?
Thanks,
Kashyap
in most of projects especially structural
Hours Per Day :8
Hours Per Week:40
Hours Per Month:172
Hours Per Year: 2000
Anyway, these rules depend on Work Conditions