Hi all
I am preparing an engineering Schedule. in which suppose any activty such Detail drawing of Compressor will contain 20 A1 size drawing. How can i refelect this in schedule.
ACTIVITY Duration Resource No Of deliverable Start Finish
Detail ... 60 Days Asst manager Eqp 20 1-Jul-11 31-Aug-11
Now i want that if i generate report that hhow many deliverable will be deliver in Jul Result will be 10 (10 for Jul) and 10 for Aug.
Thanks\\
Hi Daniel
Thanks for your responce But From the past six month i am doing the same thing but i want any different solution that i is hidden from me.I am not satisfied with this Software developer will develop something to help me.
Regrds\\
Hi Kumar,
You need to create another resource for "A1 size drawings" and treat it as material deliverable. Add the resource to P6 and enter number of deliverable to budgeted units. P6 will automatically calculate deliverable for each time period.
Regards,
Daniel