Recovery Shedule

A
Amro Ahmed 👤 Member for 17 years 5 months

Dear All

How to get recovery schedule from Project Update utlizing Global Changes

R
Ronald Winter 👤 Member for 23 years 5 months

Amro,

 

Scheduling is not something that you can do using Global Changes.  You might as well ask how to repair your car using an automatic carwash. 

 

You have to assess the reason for the delay and fix that issue.  Then you need to plan and communicate with others to determine the optimum recovery plan.  Then, you have to reflect that plan in your current schedule.  Once that is done,  you need communicate the recovery plan to others and get their buy-in.  Finally you have to work and monitor that recovery schedule.  Keep your fingers away from the Global Change function and start talking to others.  Good luck!

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts