Good morning planners
I faced problem ,How can I make comparison in (P6) between Baseline Schedule and Update Schedule so I can display in the program?
please advise
Good morning planners
I faced problem ,How can I make comparison in (P6) between Baseline Schedule and Update Schedule so I can display in the program?
please advise
You should create baseline, then set a baseline, then show the Baseline Bars and/or display the Variance columns.
If you display the Baseline bars without setting a Baseline you will display the Planned Dates which is not a good idea, so make sure you set a Baseline before displaying the Baseline bars.
Regards
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers, Consulting and Training
http://www.eh.com.au
http://www.eastwoodharris.com
http://www.primavera.com.au