comparison in (P6) ???

Good morning planners 

 

I faced problem ,How can I make comparison in (P6) between Baseline Schedule and Update Schedule so I can display in the program?

 

please advise 

P
Paul Harris 👤 Member for 25 years 1 month

You should create baseline, then set a baseline, then show the Baseline Bars and/or display the Variance columns.

If you display the Baseline bars without setting a Baseline you will display the Planned Dates which is not a good idea, so make sure you set a Baseline before displaying the Baseline bars.

Regards

Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Training Manual & Book Publishers, Consulting and Training

http://www.eh.com.au

http://www.eastwoodharris.com

http://www.primavera.com.au

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts