Hi Planners,
I have assigned the baseline to my existing current project & then i want to update the baseline with their dates & duration. But while i select the Update option it shows that the Event code error occurred & cannot update the baseline.
Is there any way to resolve this?
Regards,
Krishna
Is this standalone or client-server?
Try going into C:\Program Files (x86)\Common Files\Primavera Common\Java and run the admin.cmd utility. Log in with privuser. In the window that opens, right-click on the INTERNAL_PLUGINS configuration and click Delete. Save and exit the utility. Close and relaunch Primavera and try running baseline update again.
Let me know if this works for you.