how to update the estimated weights after applying the actuals/progress

K
kumar s 👤 Member for 16 years 4 months

Dear All

for my present project i have created the baseline and started recording the progress.

now i  have to assign some estimation weights to some of the activities.

so what is the best way to do this.

can i get it by using the update baselline option..

or i should restore and change it and assign it back

which one will be better

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts