Resource Assignment split

I have input some resources which are non-labour. The activity type is fixed duration and units. To start with the activities where Level of Effort, but then i changed them to Task dependant and ammended the dates. (i made sure that resource dates and durations matched the activities)  I then noticed a problem.

When i look at the activites on the resource usage spreadsheet, the costs differ slightly than on the activities screen, normally by  between 0.01p - £7. Not a huge amount admittedly, but im wondering why this is happening. The actvity durations are between 15hr - 27hr and they dont span long periods of time.

Has anyone any experience of this in P5. I am getting around it by removing the resource lines and re-adding them, it then seems to be perfect - but i am wondering what caused it. Any help would be appreciated.

A
Anthony Peters 👤 Member for 19 years 2 months

Thanks,

I found out it was something to do with changing an activity to Task dependant from Level of Effort, apparantly it changes the duration a fraction and therefore the resource amount fractionally.

R
Raymund de Laza 👤 Member for 16 years 6 months

Try to match the resource calendar with activity calendar and recalculate resource cost.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts