remaining units / time

 

Hello Everyone,

The activity has started on 15th of Feb & the remaining units / time remains at 15 m2/hour until 20th of March and later on it increases to 30 m2/ hour. 

I do that case manually by assigning into resource usage spreadsheet. But i would like to learn if there any special automatic tool that will increase it through activity details. And also using resource curves into the case mentioned before doesn't exactly match with the dates. Like 30 m2/hour after 20th of March. 

Here is my question; how would you increase the units / time after sometime easier? 

Regards,

Errol

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts