Options while summarizing in P6

Hi Planners,

                 Kindly inform me if there is any options in P6 to show average date while summarizing the schedule & how can we hide the dates in the summarization sheet. Kindly help me ASAP.

 

Thank you

Krishna

K
Krishna Kumar 👤 Member for 19 years 4 months

Hi Daniel,

             Thanks for your suggestion. And i've to clarify more that while summarize by groups upto level 4, i need to see dates on 2,3,4th level, but in my 1st level i've hide it. is it possible? i hope that you understand my question. Kindly give me your advice ASAP

Thank you,

Regards,

Krishna

K
Krishna Kumar 👤 Member for 19 years 4 months

Hi Daniel,

             Thanks for your suggestion. And i've to clarify more that while summarize by groups upto level 4, i need to see dates on 2,3,4th level, but in my 1st level i've hide it. is it possible? i hope that you understand my question. Kindly give me your advice ASAP

Thank you,

Regards,

Krishna

D
Daniel Limson 👤 Member for 24 years 7 months

 

Krishna,

In summary, P6 will use the earliest start date and the latest finish date to calculate the total duration of the summary bar and it uses calendar days at 7 days per week.

If you do not want to see the Start and Finish Dates , you can always remove the column.

 

Best regards,

Daniel

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts