data not coming through on import

 

 

I have an issue whereby upon mporting a contractors programme into our p3e it is ignoring the role dates assigned to an activity

 

for example a activity has 1 resource attached with a finish date 13th Dec 2010 and 3 Roles attached with a finish date of 31st Jan 2011 (all driving the activity dates) however the activity finish date is 13th dec.

 

I have the text file which accompanies the xer sent from the contractor and this confirms that the finush date on the activity should be 31st Jan

 

im am using p3e version 5.0  - the contractors programme is also version 5.0

 

any suggestions?

 

Thanks

D
Dieter Wambach 👤 Member for 19 years 4 months

Hi Simon

Just an assumption: With the import you create a new project. Then some parameters for this new project are taken from the default project.

I would check if "drive activity dates by default" is unmarked - view Projects --> Resources. If not unmark and for the activities as well - view "Assignments".

Good luck!

Dieter

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts