Activity Percentage Complete vs Schedule Percentage Complete

I
Irfan Khan 👤 Member for 16 years 10 months

 I am working in a construction company and I prepared a cost loaded schedule but I am confused while updating of my schedule.

Schedule Status:         Duration Type = Fixed Duration & Units

                                % Complete Type = Physical

WBS Status:               I defined 4 phases

                                    1 = General Requirements (not cost Loaded)           

                                    2= Design Drawing (not cost Loaded)           

                                    3=Construction Phase (Cost Loaded)

                                    4=Project Close Out (not cost Loaded)

Problem: While updating the Percentage to activities which is under General Requirements or Design Drawing the band of WBS is not showing overall percentage of that WBS.

Inspite WBS of General Requirements or Design Drawing, Construction Phase is showing percentage on its bands & whenever I am giving percentage to Activities (in the column of Activity % Complete) 50% the Schedule % complete showing 100%.

  1. How these parameters are working please explain somebody?                    
  2. So can somebody tell me how to show percentage on band of these two WBS bands?   
  3. Which is the best way to update your schedule ?

Please reply somebody …..i ill be highly obliged

 

Thanks

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts