Dear All, Primavera P6 "While creating Resource Histogram by Using Resource Usage Profile (Resource Histogram), The X-axis is Time Scale (by Default) But Y-axis is coming in Hours (h) , i need it in "Numbers" Say Example, im generating Resource Histogram for Resource " Brick " it is already a "material" type Resource having unit of measure " Numbers " This i created thro Admin Categories ---> Unit of Measures While generating Resource Histogram for brick material as i said above, it is coming for me in Y-axis unit is 'h' like 20h , 40h, 60h i need this in Numbers like 20n, 40n, 60n or 20 No's , 40 No's , 60 No's like that Need HELP !!!! MOST URGENT !!!!!! Thanks in Advance
You can not customize Y-axis in resource histogram. P6 does not support.