Budgeted Cost

R
Rohit K 👤 Member for 18 years 1 month

Hi All,

This is relating to the Budgeted Cost (BC). When I scheduled for the first time after entering the labour and price for the activities the BC for only some of the activities were displayed, that too at sometimes only for 1 or 2 resources if I had 4 - 5 resources assigned to that acivity. After some readings and research I inserted the Cost Unit Linked in the Activity Layout ticked for each of the resource for the activity then the BCs were displayed.

Why is this so? Isnt there any default wherein the BCs are displayed without doing this manual procedure?

Any responses to help in this matter will be appreciated by the planners.

Rohit

F
Ferdinand U. 👤 Member for 18 years 10 months

hi

if its the COST UNITS LINKED

you can use global change to replace it to YES or NO (whichever you want)

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts