I have a schedule with a base callender of 8hrs per day. when I add activities and give them a specific callender of 24 hrs per day I have to enrter 3 days into the duration column to get 1 day between the early start/early finish dates. Does anyone have any idea how to solve this? Thanks, Mark
Primavea 6.2.1 callenders