Importing from P3 to P6 Cost Difference

Hi All,

 

I Have a small Problem in Importing a Units & Cost Loaded P3 schedule to P6, the cost doesnt seem to match even though All the calculations based on the P3 Software are correct, there seems to be a problem in some Cost decimals when you convert the P3 to P6.

There is no Problem within the Units Value; there is no units Variance, but when you get to the Cost Computations, there is a decimal value difference, what seems to be the problem?

I always use "Recalculating assignment cost using units & prices" when importing using the very same cost, units, price & resource details in P3.

 

Need your Help. Thank you.

 

Regards,

 

Ronnel Anthony Celerio