Automatic update of duplicate activities in separate projects?

Hi all,

This is our situation:

There is one Master schedule (Project 1). There are three separate (P2, P3, P4). Project 1 consists of some unique activities and some activities identical to those in P2, P3 and P4.

Those activities in P1 are linked to the original activities in P2, P3, P4 by Start to Start logic. The intent is to manually update P2, P3 and P4. My question: is there a way to automatically update the same activities in P1 (because we want them to rreflect the same info)?

Thank you very much.

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts