Hello ,
Explication :
Imagine we have a Labour who works 8h/day and an excavation task ,
the original duration of the task is 10 days
so ,this laber will work a total of 80h ,
If i change the original duration to 2 days ,normally this laber have to work 40h/day => 5 labers/ day
But in the table we have always 8h/day (unit/time) =>one laber only
Thank you
Hi,
What is meant by "Explication" as you telling in first line?
ty.
Hi,
What is meant by "Explication" as you telling in first line?
ty.
i want to say "fixed duration and units" and "fixed units" should produce the same results.
Glad to be of help :)
Good morning
Thank you for this very interesting table
Hi,
Change "Duration Type" to "Fixed Units" in the activity and you would be able to see the changed rate. By default your "Duration Type" would be " Fixed Duration & Units".
Duration Type follows following formula :
hence changing the Duration Type affect the resource and duration calculations in the following ways :
Duration Type
Change Units/Time
Add 1st resource
Add additional resources
Fixed Units/Time
Duration
Units
Duration
Fixed Duration & Units/Time
Units
Units
Units
Fixed Units
Duration
Units
Duration
Fixed Duration & Units
Units
Units
Units/Time of each Resource