Is it possible to use weighting for rolled up performance % complete.
I have noted that as long as the budgeted units >0 then performance % complete rolls up. However the performance %complete does not change whatever the number of units is e.g. if 2 activities have 1hr each the rolled up percent complete is the same as if 1 activity has 1hr and the other has 1000hrs.
Can anybody help?
Thanks Arend
Hi Dave.
Performance percent complete uses the Total cost per activity as a weighting.
So the answer lies in your resource rates. If you use a rate of 1$/h you are then effectively using your budgeted units as a weighting.