dear all
i have finished recording progress for the project.
all the activities are now 100% complete
but due to some updation problem i still have the difference between the actual labour units and budgeted units.
all the activities are resource loaded.
and progress monitoring is done in units % complete.
so now i want to show the schedule variance labour units(budgetedunits-actaul units)as zero for all the activities.
i wanted to change this using the global change instead of going to each activity and updating.
so can anybody please tell me the global change criteria for doing this.
thank you