i am handling 2 projects in the present shutdown.
both the projects have baseline attached.
now i am half the way in the project.
now when i open the project in my colleagues computer the baseline start and finish is showing same as the current start and finish.
this is happening only for 1 project.
in this project i have kept 2 projects as baseline but have assigned the 2nd project as baseline.
so other than my computer in all the other computer it is not showing correctly.
what may be the reason
please advice
thank you
why baseline Finish and Planned finish is Showing same
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
When you export a project from your system and Import into other PC, only the project with actuals (without baseline) will exported. So when you open it in other PC, It will show only actuals as there is no baseline attached to it. First, go and check whether baseline is attached to that project or not(In other PC). If not restore/copy the baseline as a seperate project and export that baseline(.xer) (from your PC). Now, assign this baseline to the project. Then you can see the baseline dates against actuals.
If the layout calls for a Baseline and no baseline schedule is assigned, P6 will display the Planned dates instead without warning you that this is going on. Check you baseline schedule assignments. Good luck!