Chain of Predecessors

Is it possible to create a filter or something similar to see the chain of predecessors without having to use the trace logic function? I do a fair share of work in Pertmaster which has this set up as a filter already. I specify a filter to start at a particular milestone and it will filter out only the activities that have logic ties that go through this particular milestone. It works the same going the other way if I want to see what the chain of sucessors are. This is particularly helpful when needing to identify impacts to the milestones as well as impacts that milestone may cuase if it is late. I would prefer a graphical representation and not just a report, but I will take that too if I can select a particular milestone and not the entire project. 10,000+ activities will create a very large report.

 

Thanks.

 

-JW

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts