I think I agree with your first statement, but not quite sure I understand the second. Are you saying that eg. Steel accounts for 20% of our total construction workhours and we are 50% complete (by ton) with steel erection, then we have earned 10% of total construction progress? If so, then we agree. The reported construction progress is the aggregate of craft earned hours divided by the total construction workhour budget/estimate.
Workhours 'normalizes' comparison of disparate activities - pipe, wire, foundations, etc. - for earned hours (against established budget/estimate), but not for actual progress, that comes from installed quantities.
Second step is to compare the hours expended to what was allocated, but that was not the question.
It should not be confusion between relative weight of activities to each other (based on cost or M/H) and progress measurement.
Explaining:
Method of measurement for construction should stick allways to physical progress of the works such as Units, m3, klms, tons, etc, done. Then comparing with the total qty to be done it comes a % achieved.
Since normaly you have activities with diferent units of physical work (m3, tons, m2, etc) then you have to use the same unit to relative calculate all the progress of the works - therefore MH is the comun unit to give a relative weight to each activity.
Summarizing:
M/H - Use as units for work qty and as relative weight of each activity.
Qtys (m3, m2, tons, inches) - Use for physical progress of works.
Choosing between M/H and cost: Depends on the kind of projects, activities, etc. Basically boths are suitable.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Jose;
I think I agree with your first statement, but not quite sure I understand the second. Are you saying that eg. Steel accounts for 20% of our total construction workhours and we are 50% complete (by ton) with steel erection, then we have earned 10% of total construction progress? If so, then we agree. The reported construction progress is the aggregate of craft earned hours divided by the total construction workhour budget/estimate.
Workhours 'normalizes' comparison of disparate activities - pipe, wire, foundations, etc. - for earned hours (against established budget/estimate), but not for actual progress, that comes from installed quantities.
Second step is to compare the hours expended to what was allocated, but that was not the question.
Thanks For your reply.
I appreciate your advise to measure physical progress based on Qty. ton Mtr. etc.
Construction Progress measurement To calculate the Weight Values for all activity , based on Manhours is easy for me.
Why, M/H based on the Qty ( according to work productivity) (4 Kg/h for Steel fabrication)
Example . if 1000 M/h spent on Fabrication , I can achived the Fab qty 4000 Ton for Steel structure fabrication.
may some other planner using Cost for the same, if they are using Cost then why, they are not chosing M/H
I want your experience in that.
Thanks so much in advance,
have a nice week end
Good morning Shazia,
It should not be confusion between relative weight of activities to each other (based on cost or M/H) and progress measurement.
Explaining:
Method of measurement for construction should stick allways to physical progress of the works such as Units, m3, klms, tons, etc, done. Then comparing with the total qty to be done it comes a % achieved.
Since normaly you have activities with diferent units of physical work (m3, tons, m2, etc) then you have to use the same unit to relative calculate all the progress of the works - therefore MH is the comun unit to give a relative weight to each activity.
Summarizing:
M/H - Use as units for work qty and as relative weight of each activity.
Qtys (m3, m2, tons, inches) - Use for physical progress of works.
Choosing between M/H and cost: Depends on the kind of projects, activities, etc. Basically boths are suitable.
Hope it helps you.
BR
JMFrade