Dear all

              I would like to have some information form you regarding changes/up-gradations in P6 version7 to its lower versions. Recently, my company PC has been installed with P6.7. So information regarding this will be extremely helpful.

N
Naveen Paladugu 👤 Member for 15 years 11 months

Mr. David. Thank you  for your informative reply. Could please explain what is wrong in summary of TF values.

D
David Johnstone 👤 Member for 21 years 9 months

One of the most awaited "enhancements" is that way you can now show durations in days based on the individual task calendar.

You will first need to set-up each Calendar, and ensure you specify what a day;week;month;year represent in hours. These settings are then used to "calculate" what a "day" is when you choose to show your durations in days rather than hours.

Version 7 still has a few "flaws," one being the roll-up or summary of TF values.

Setting the height of activity bars is still done by choosing between "thick,thin,skinny" bars if you are using the Windows Client.

Ask your vendor for information on any other enhancements...

Have fun!

N
Naveen Paladugu 👤 Member for 15 years 11 months

In continuation with the above subject, here, I am giving some that I have been found in P6 Version 7. Please correct me If any thing to corrected or added. And please add new points.

1) Progress line has been added. It displays progress with respect to data date in bar chart area. 

2)Re-numbering of activity Ids.

3)Planned start & Planned finish columns has been added.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts