Guys,

 

Actually I've problem everytime I send them schedule, the activity codes broken and i realized this happen due to diffrent global and project codes. Is it any of you can brief me what is the best way to transfer activity codes from project to global

 

Your helps on this matter is highly appreciated

Thanks

I
Izam Zakaria 👤 Member for 20 years

yes correct, but I'm updating live schedule which every month we will include a hundred new activities :(

so i just simply copy the codes and transfer like that?

D
Daniel Limson 👤 Member for 24 years 7 months

 

Oh yes, regarding your question, you can actually copy and paste the activity codes from Project to Global

Regards,

DL

D
Daniel Limson 👤 Member for 24 years 7 months

Hi Izam,

When you send out an exported schedule, the activity codes should still be there. They just need to sort or group the activities according to your grouping. You need to instruct them that you are using Activity Codes instead of WBS and also tell them how the programme is sorted.

Cheers,

Daniel

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts