Hi experts
I have encounter a problem, start milestone finish time is showing 4 PM. ( the cal i am using for this mile stone is 9 Am to 6 PM)
while i have linked activities with this mile stone all activities finsh time is 4 PM insted of 6 PM,
I have faced same problem before , then i solved that to change the duration and relation.
however now i have try to do the same but it is not working.
Could you please share your advise.
Regards
Shazia,
Try changing your working hours through the project calendar. Go to Enterprise, Calendars and then select projects and add calendars you are using and then modify the working hours. It should solve your problem.
Best regards,
Daniel