MILE STONE FINISH TIME CHANGE

S
Shazia khan 👤 Member for 18 years 1 month

Hi experts

 

I have encounter a problem,  start milestone finish time is showing 4 PM. ( the cal i am using for this mile stone is 9 Am to 6 PM)

while i have linked activities with this mile stone all activities finsh time is 4 PM insted of 6 PM,

 

I have faced same problem before , then i solved that to change the duration and relation.

 

however now i have try to do the same but it is not working.

Could you please share your advise.

Regards

D
Daniel Limson 👤 Member for 24 years 7 months

Shazia,

Try changing your working hours through the project calendar. Go to Enterprise, Calendars and then select projects and add calendars you are using and then modify the working hours. It should solve your problem.

Best regards,

Daniel

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts