Hello Guys,
I leveled the resources and the resource profile to me looks fine. I want to acknowledge the leveled dates but the problem is when I hit schedule, the dates go back to previous settings, even after I have unchecked the "Preserved scheduled early and late dates" option under level resources dialog box.
Any help will be highly appreciated.
Thanks
Ijaz
Hi
when you click the resource leveling icon There is a check box option in the pop up window which states to consider scheduling with resource leveling.
cheers
K
Ahmad,
when you hit F9 after your project has been resource-leveled, P6 reschedule the project based on links between activities and date constraints; this means you will lose the result of leveling
to acknowledge the result of leveling, change the links between activities to take into account the new start dates of the activities based on the resource availability
Alexandre