Acknowledging the new dates after Resource Leveling

I
Ijaz Ahmad 👤 Member for 19 years 10 months

Hello Guys,

I leveled the resources and the resource profile to me looks fine. I want to acknowledge the leveled dates but the problem is when I hit schedule, the dates go back to previous settings, even after I have unchecked the "Preserved scheduled early and late dates" option under level resources dialog box.

Any help will be highly appreciated.

Thanks

Ijaz

S
Satish Kumar 👤 Member for 16 years 3 months

Hi

when you click the resource leveling icon There is a check box option in the pop up window which states to consider scheduling with resource leveling.

cheers

K

A
Alexandre Faulx-Briole 👤 Member for 23 years 4 months

Ahmad,

when you hit F9 after your project has been resource-leveled, P6 reschedule the project based on links between activities and date constraints; this means you will lose the result of leveling

to acknowledge the result of leveling, change the links between activities to take into account the new start dates of the activities based on the resource availability

Alexandre

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts