is there anything wrong with p6 v7

R
Rola Sabbah 👤 Member for 16 years 6 months
G
Gene Beam 👤 Member for 22 years 8 months

I came across this a few months ago and I found that when you copy and past some activities they bring across dates in the fields called External Early Start and External Early Finish. I think this was because I was copying completed activities. Just clear any dates if the External Early Start and External Early Finish.

G
Gary Whitehead 👤 Member for 17 years 2 months

I’m sure you’ve checked this, but has the activity got an actual start date?

N
niles luo 👤 Member for 20 years 6 months

hi,

pls check that this activity does not have relationship from other project.

Best Regards,

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts