Creating Progress Charts...

A
Alex Cook 👤 Member for 15 years 9 months
G
Gary Whitehead 👤 Member for 17 years 2 months

Assuming by ’scheduled’ you mean ’baselined’:

go to view, bars and make sure the baseline, actual & remaining bars are selected for display