BL 1 Start Dates Slip once we assign actual start

R
Rodel Marasigan 👤 Member for 19 years 7 months

Izam,

When actual start has been tick and data date move the Baseline will slip if the remaining duration was not change. You need to adjust remaining duration to keep the planned finished date if progress was as planned.

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts