Kumar,

Global change will affect only the assigned resource to open project (Filter or non-filter) based on criteria.



If you are using Activity UDF it will not be present to Resource Assignment UDF because resource assignment has its own UDF. It is like Activity Code-> to Activity, Resource Code-> to Resource, Project Code-> to Project...etc...