Can somevody explain ......?
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Thanks to all of you.....
Irfan,
That is the basic element of Earned Value Management.
Planned Value = BCWS (Budgeted Cost Work Schedule)
Earned Value = BCWP (Budgeted Cost Work Performed)
Actual Value = ACWP (Actual Cost Work Performed)
Budget At Completion = BAC (Budget assigned to Project)
Estimated At Completion = EAC (Total Forecast Cost)
Estimated To Complete = ETC (Remaining cost to complete)
Hi Irfan
\check this link out
https://acc.dau.mil/CommunityBrowser.aspx?id=241394
hi Irfan
Planned value - Budget * % planned progress
Budget at completion = Actual cost + Remaining cost
Regards,
Balaji