PLANNED PERCENTAGE
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Kumar,
U never produce S-Curve(xls) from P6 before? it is the same method right? but u have to select the option "Tabulated by days" from there u can get your tabulation by daily.
If i did expalin this wrongly, guys u are pleased to correct me.
Hi Kumar,
Option-1
one way of doing this is to assign a resource which is uptwhich shall take the duration of every activity as the budgeted quantity which will help you in arriving at a planned percentage on exporting the budgeted values per month to excel or you can go for the resource profile month wise to get the palnned percenatge.
Option-2
other way is to assign resources - labour.material and plant/ equipment which will be the more accurate way of doing it but....as you know it is an uphill task .
may be option 1 willl help u in this case.
cheers
Copy your schedule in excel and do it there it is much easier
hi kumar,
what i do is to save another copy of the program and then use apply actual function and you will see the planned precentage and then compare it to the actual.
and if you want in advance you can put the data date in the next day date and then subtracting the previous percentage, but i think it will be time consuming