Budget Unit Calculation
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Sir Andrew Dick
Thank you for your advice sir,may be its better to ask the person who created the programme on how he calculated the budget unit per activity.
thanks and regards
Luis
Luis,
I would suggest that the figures entered may be a dollar value associated with the activities.
These numbers may (should) have come from the project estimate.
You generally wouldnt let the planning tool create a value on a discrete effort/labor activity, as this information is usually entered manually.
I would ask the planner that created the schedule how they arrived at that figure and if the answer is an estimate then request a copy of it as you may wish to refer to it at a later date.
Andy