Thank Rodel for very quick reply.
Best regards,
Duy
Dear Duy Pham,
Yes you are doing it correctly and very useful in Earned Value Management, Progress Reporting, Baseline Comparison, Cost Management, Forecast and Cash Flow and many other useful reports like S-curve, Histogram etc...
Good Work!
Best Regards,
Rodel