Store Period Performance

R
Rodel Marasigan 👤 Member for 19 years 7 months

Rifky,

Unfortunately not both at the same time. You can either show % complete or Units and Cost.

Percent complete can be showed using Spreadsheet Options-> Calculate Average then enter the total cost or unit over 100.

For Planned use Period Planned Value Cost or Unit and for Actual use Period Earned Value Cost or Unit.

R
Rifky Soedirdja 👤 Member for 16 years 1 month

Thanks Rodel.

Is it possible to show % complete for that Period also besides the Units, Cost, etc?



Rgds,



Rifky

R
Rodel Marasigan 👤 Member for 19 years 7 months

Rifky,

Don’t use Actual Labor unit field from Units and use Financial Period Value instead on your spreadsheet. That is where all the data stored (i.e. Period Actual Labor Unit, etc…). Using original data will proportion from actual start to data date.

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts