Difference in % Complete

R
Rodel Marasigan 👤 Member for 19 years 7 months

Ernani,

Generally it refers to Actual % complete.

1. Cost % Complete = % of Actual cost entered to activity.

2. Duration % Complete = % of Actual duration complete entered to activity

3. Expense Cost % Complete = % of Actual Expense cost entered to activity

4. Labor Cost % Complete = % of Actual Labor cost assigned to activity

5. Labor Units % Complete = % of Actual Labor complete assigned to activity

6. Material Cost % Complete = % of Actual Material Cost complete

7. Units % Complete = % of Total Actual Units (labor + non labor)

8. Activity % Complete = refers to any activity type set to activity (i.e. Duration %, Unit % and Physical % type)

9. Performance % Complete = Activity % complete with summary.

10. Physical % Complete = % of physical effort (manual input)

11. Schedule % Complete = Planned % complete based on Baseline assigned. If no baseline assign by default it use current project.



Planner are subject to progress only on the settings correspond to those Progress complete type when updating the progress. Majority of those percent complete synchronize on the settings and automatically updated except for Physical % complete type.

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts