Project Progress

R
Rodel Marasigan 👤 Member for 19 years 7 months

Arun,

Activity % Complete = Performance % Complete = to any Percent complete type selected.

Activity % complete don’t have summary but Performance % complete have.



If depends how you want to update and monitor your progress. Make sure you maintained and assigned baseline first.

If you use Physical % Complete every thing needs manual update (i.e. remaining duration, At Completion if different to budget)



If you use Duration type combined with Fixed Duration and Unit or Fixed Duration and Unit/Time it will synchronized the update of Remaining and At completion.

A
A.Jaffer Sadiq 👤 Member for 17 years 8 months

Hi



You can take Physical Completion %



Because you’re not done resources load program. If that



program resources loaded means you can take Activity%



completion, you will get correct % Completion of your project.



This only Vertical Project this suitable,



Ok thanks



Jaq

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts