Setting timescale Gantt - P5

R
Rodel Marasigan 👤 Member for 19 years 7 months

Conrad,

The only setting on Timescale that show day date is using Three line and select Day Shift as Date interval. The last line will be showing 0 if no nightshift calendar used.

C
Conrad Cannella 👤 Member for 17 years 6 months

Thanks for the timely rispost.Molto bright as ever. But maybe I explained bad. I wanted to display the corresponding number of weekday and not a progressive. For example, in the year 2010 the first level, second level the months and third level the number of days of that from day 1 to day 30, one month from day 1 to 31, etc. ...

Thanks a lot

R
Rodel Marasigan 👤 Member for 19 years 7 months

Conrad,

Right click on Gantt Chart area and select Timescale.

Tick Show Ordinal date and select the date interval you want to use and change the Start date to match number value you wanted to show. If you wanted to show both click Three Lines and you can select both.

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts