P6 - calculate rem. units based on Activity % comp.
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Abhijeet Ranadhir,
If your duration type is either Fixed Duration & Units or Fixed Duration & Unit/Time and Percent Complete type is Duration % then updating % complete will automatically update Actual & Remaining duration (synchronise update). If you are using Physical % for Percent Complete type then everything is manual input.