Activity type Selection

K
kumar s 👤 Member for 16 years 4 months
R
Rodel Marasigan 👤 Member for 19 years 7 months

Kumar,

You can use Task Dependent for both running parallel and a successor of Shutdown activities.



Ex:

Scaffolding erection -> FS -> Shutdown

Insulation removal -> FS -> Shutdown



If the Insulation crews required scaffold to remove insulation then -> Scaffolding erection-> FS ->Insulation Removal-> FS->Shutdown



If Insulation crews can start from the area where scaffolding are finished and continue to erect scaffold on other area where insulator crew is not required then -> Scaffolding erection -> SS + say 5 days lag Insulation removal-> FS -> Shutdown, Scaffolding erection -> FS -> Shutdown