Where i can see my baseline program after assigning

Z
Zoltan Palffy 👤 Member for 16 years 11 months

you cant its locked away and hidden its designed that way. ALWASY ALWAYS as Raviraj said make a copy of the baseline this way if you need to reference it you can do so. 

A
A D 👤 Member for 19 years

Always copy baseline program before assigning it, so that if required, you can open baseline later on.

R
Rodel Marasigan 👤 Member for 19 years 7 months

You will not see baseline once assigned because it resides at the background. You can always open it by restoring the baseline if you need modification and maintain it back. If you just want to read the data show column start with BL? and same on Gantt Chart (Depends which one you use, project, primary, secondary...etc...)

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts